R.S.M. 1987, c. P70
The Pipe Line Act
Table of Contents
1 | Definitions. | |
PURPOSE AND APPLICATION | ||
2 | Purposes. | |
3 | Application. | |
PART I
CONSTRUCTION PERMIT |
||
4 | Issue of permit before construction. | |
5 | Application for construction permit | |
(2) | Further information. | |
(3) | Copy of material for Minister of Highways and Transportation. | |
6 | Entry on lands for surveys, etc. | |
7 | Notice of application. | |
8 | Circumstances to be considered. | |
9 | Public hearing by board. | |
10 | Reference to L. G. in C. | |
(2) | Order respecting grant of construction permit. | |
11 | Alteration in pipe line. | |
(2) | Making of alteration. | |
(3) | Powers of minister respecting alteration. | |
12 | Order to alter pipe line. | |
13 | Construction across or near highways. | |
(2) | Form of consent. | |
14 | Notice to remedy default. | |
(2) | Revocation or suspension of permit. | |
(3) | Revocation on request by permittee. | |
PART II
TAKING AND USING LAND |
||
15 | Definition of "right of user". | |
(2) | Form of grant of right of user. | |
(3) | Documents to accompany grant of right of user. | |
(4) | Conditions under expropriation. | |
(5) | Effect of right of user. | |
(6) | Previous registrations. | |
(7) | Terms and conditions of approved form. | |
16 | Expropriation. | |
(2) | Agreement prior to expropriation. | |
(3) | Limitation of right of expropriation. | |
(4) | Expropriation of additional lands. | |
(5) | Construction across highways. | |
(6) | Manner of entry upon and use of lands. | |
(7) | Deposit of plans before expropriation. | |
RESTRICTIONS | ||
17 | Title to mines and minerals. | |
18 | Working mines and minerals near pipe line. | |
(2) | Application for leave to work mines and minerals. | |
(3) | Notice of application. | |
(4) | Grant of leave to work mines and minerals. | |
PART III
OPERATION OF A PIPE LINE |
||
19 | Operating licence. | |
(2) | Application for operating licence. | |
(3) | Issue of licence. | |
20 | Filing of plan in land titles offices. | |
(2) | Preparation of plan. | |
21 | Application for revocation of licence. | |
(2) | Basis of application. | |
(3) | Notice of application. | |
(4) | Reference to L. G. in C. | |
(5) | Order of L. G. in C. | |
(6) | Application for reinstatement and procedure. | |
22 | Public Utilities Board Act not applicable. | |
(2) | Application to declare pipe line a public utility. | |
(3) | Disposal of application. | |
(4) | Order of L. G. in C. and effect thereof. | |
(5) | Recommendation of P. U. Board for revocation, etc., of licence. | |
(6) | Saving. | |
(7) | Reinstatement. | |
PART IV
EXEMPTIONS |
||
23 | Special exemptions. | |
(2) | Conditions of exemption. | |
PART V
GENERAL |
||
24 | Alterations. | |
25 | Discontinuance. | |
(2) | Discontinuance of exempted pipe line. | |
26 | Public safety. | |
27 | Compensation for damage. | |
28 | Assignment of permits and licences. | |
29 | Effect of revocation, etc. | |
30 | Registration of address. | |
31 | Liability for damage to highways. | |
32 | Regulations. | |
33 | Saving. | |
PENALTIES AND OFFENCES | ||
34 | Obstruction of pipe line. | |
35 | Contravention of Act or regulations. | |
36 | Obstructing the minister. | |
37 | Concurrent remedies. | |
SCHEDULE | ||
THE PIPE LINE ACT | ||
GRANT OF RIGHT OF USER |